Location:  20 Bentick Street, London, W1U 2EU
Status: Complete
Lift: Duplex Modernisation

SCOPE OF WORKS:

 

Replace 2 x Existing Lifts with Conventional MRL Lifts

Improve reliability and install open protocol control system

Upgrade doors with a more robust equivalent

Add trimmer steels to shared shaft and install shaft division screens

 

 

EQUIPMENT USED:

 

CTV Lifts

Ziehl Abegg Gearless motors

Selcom Pegasus landing doors and car door operators

Lester Almega 2 Control Panels

Dewhurst Push Buttons

Bespoke high end lift interior by Marcos

​​

BP_TargetLifts-024.JPG
BP_TargetLifts-001.jpg
BP_TargetLifts-010.JPG

Duplex Modernisation

Features

Travel 

15M

Stops

6

Speed

1.0MS

Weight

825KG

  • The installation of this duplex pair of lifts was especially challenging due to the building décor and logistics

  • This was a very busy office building which had recently been decorated with clean modern finishes

  • All working areas were fully protected and hoarded to avoid unnecessary damage

  • Prior to removal of the existing lifts, the project team installed new trimmer steels between the two lifts. This enabled the new conventional lift designs to be installed. We were also able to separate the shafts by fitting new shaft division screening

  • One big challenge was to design the lift installation so the door openings would be in the exact same position as they were originally. No building works were to be undertaken so there was no room for error

  • A duplex installation completed on programme to a very satisfied client